Installation of stainless steel pipelines

Read more ...

Object: Mondi Stamboliiski EAD
Implementation period: 2018
Scope: Construction of stainless steel pipelines according to isometric schemes

Installation of stainless steel pipelines for the food industry

Read more ...

Object: "Waffles Day and Night"
Implementation period: 2017
Scope: Design, supply and installation of stainless steel pipelines between existing and new production plant

Complete construction of a sunflower oil refinery

Read more ...

Subject Title: Complete construction of an oil refinery
Implementation period: 2016 - 2017
Scope: Installation of carbon and stainless steel pipelines, condensate and steam pipelines.

Construction of a new plant for the production of alcohol

Read more ...

Object: Zaharni Zavodi AD
Implementation period: 2016
Scope: Delivery and installation of stainless steel pipelines for a new installation for alcohol.

Construction of an installation for secondary cleaning of the electrolyte

Read more ...

Object: Aurubis Bulgaria AD
Implementation period: 2016
Scope: Delivery and installation of technological steel pipelines made of carbon steel, stainless steel pipelines and polyethylene pipes.

Installation of stainless steel pipelines

Read more ...

Object: Kamenitza AD
Implementation period: 2015
Scope: Installation of stainless steel pipelines for new production plants

Construction of stainless steel pipelines

Read more ...

Object: Mondi Stamboliiski EAD
Implementation period: 2015
Scope: Delivery and installation of stainless steel  pipelines for condensed methane, manufacture and installation of pipe supports.

Construction of plant for raw oil production - Kostinbrod

Read more ...

Object: "New Oil" AD

Implementation period: 2014-2015

Scope: Construction of new boiler (steam plant), construction of steam steel pipelines and heat pipelines , heating installation for production workshops "Press workshop" through heaters and radiators.

Construction of plant for raw oil production - Kostinbrod

Read more ...

Object: "New Oil" AD

Implementation period: 2014-2015

Scope: Installation of all technological steel pipelines, raw oil pipelines, steam steel pipelines and heat pipelines, pipelines around boiler (steam) plant.

Installation of industrial steel pipelines

Read more ...

Object: "PB Consortium" AD

Implementation period: 2014

Scope: Installation of industrial steel pipelines from carbon steel and stainless pipelines for sulfur installation at the territory of "Lukoil" Burgas.

Steel pipelines installation

Read more ...

Object: "Kamenitza" AD

Implementation period: 2014

Scope: Delivery and erection of steel pipelines from carbon and stainless steel, installation of fittings and fixtures.

Installation of technological steel pipelines

Read more ...

Object: "Evricom" EOOD

Implementation period: 2014

Scope: Construction of steel pipelines for paraffin unloading, heat distribution applying, heat insulation and cladding.

Installation of industrial steel pipelines

Read more ...

Object: "CBMI Construction Co. Ltd - branch Bulgaria"

Implementation period: 2014

Scope: Installation of technological steel pipelines, fittings and fixture in processing rain water station for project "New production line of Devnya Cement".

Installation of steel pipelines

Read more ...

Object: "Linde Gas Bulgaria" EOOD

Implementation period: 2013

Scope: Delivery, fabrication and installation of technological steel pipelines from carbon steel, stainless steel pipelines, pumps, fittings and fixture for production installation for gaseous oxygen at the territory of "KCM" AD.

Installation of industrial steel pipelines

Read more ...

Object: "Fraport Twin Star Airport Management" EAD

Implementation period: 2012

Scope: Delivery and installation of technological steel pipelines for reconstruction of storage for fuel-lubricant material (GLM), delivery and installation of measuring appliances.

Installation of industrial steel pipelines

Read more ...

Object: "Invensis" EOOD

Implementation period: 2012

Scope: Installation of technological steel pipelines from carbon steel for workshop "Extraction" of oil plant "Papas Oil" -Qmbol.

Construction of fire extinguishing installation

Read more ...

Object: "Maritsa Oil" AD

Implementation period: 2012

Scope: Construction and installation of a drencher fire extinguishing installation for workshops "Press" and "Extraction" of the plant for production of vegetable oils "Maritsa Oil" AD, Yasen village, Pleven municipality

Construction of installation for utilization of biogas

Read more ...

Object: "Topaz Mel" OOD

Implementation period: 2012

Scope: Design, construction and commissioning of biogas utilization installation, through combustion for heating of buffer tank 600 m3, including installation of carbon steel and stainless steel pipelines for biogas transfer, fittings installation, fixture and equipment.

Construction of plant for vegetable oil production - village Yasen, municipality Pleven

Read more ...

Object: "Maritza Oil" AD

Implementation period: 2012-2014

Scope: Installation of industrial and technological steel pipelines around equipment, installation of stainless steel pipelines and fixture, pipeline heat insulation.

Construction of New lead production

Read more ...

Object: "KCM" AD

Implementation period: 2012-2014

Scope: Preliminary fabrication and erection of carbon and stainless steel pipelines, steel pipelines around boiler and installation of gases purification, installation of fittings and fixture.

Fabrication and erection of stainless steel pipelines

Read more ...

Оbject: "Aurubis Bulgaria" AD

Implementation period: 2012

Scope: Fabrication and erection of steel pipelines and equipment from stainless steel SX, installation of stainless steel pipelines, fittings and fixture, installation of fridge equipment.

Installation of technological steel pipelines

Read more ...

Object: "Invensis" EOOD

Implementation period: 2011

Scope: Installation of technological steel pipelines from carbon steel for workshop "Extraction" of oil plant "Papas Oil"- Balchik.

Reconstruction of boiler plant

Read more ...

Object: "ZMM Nova Zagora" AD

Implementation period: 2011

Scope: Relocation, reconstruction and gasification of boiler plant.

Installation of steel pipelines

Read more ...

Object: "Ognyanovo-K" AD

Implementation period: 2011

Scope: Preliminary fabrication and installation of all steel pipelines and fixture, necessary for installed mechanical installation works assembling, installation of steel pipelines for fuel (petrocoke), steel pipelines type "lancet", hydraulic installations.

Construction of fire installation

Read more ...

Object: "Star Bat Bulgaria" Ltd.

Implementation period: 2010

Scope: Construction and installation of a sprinkler fire extinguishing system at the Carrefour hypermarket - Tsarigradsko Shosse Blvd., Sofia

Installation of pipelines from carbon steel (black pipelines)

Read more ...

Object: "Rubin" AD

Implementation period: 2010

Scope: Delivery and installation of steel pipelines for air and vacuum, steel pipelines for cooling system, installation of copper pipelines for bubble system.

Construction of heating installation

Read more ...

Object: "Kaproni" AD

Implementation period: 2010

Scope: Construction of gas and heating installation, panel heating.

Gas installations and heating installations

Read more ...

Object: State opera "Stara Zagora"

Implementation period: 2006-2010

Scope: Complete reconstruction of state opera "Stara Zagora", construction of gas and heating installation of the building is part of it.

Rehabilitation of existing equipment and technology implementation for nitrogen and phosphorus purification of Sofia WWTP for Waste Water "Kubratovo"

Read more ...

Object: "ISA 2000" EOOD

Implementation period: 2010

Scope: Fabrication and erection of all stainless steel pipelines, carbon steel pipelines and preliminary insulated pipes, installation of fittings and fixture.

Fabrication and erection of steel pipelines for SWEP

Read more ...

Object: "Kamteks 2000" OOD

Implementation period: 2009

Scope: Fabrication and erection of equipment and steel pipelines for SWEP "Uhlovitza".

Gas duct construction

Read more ...

Object: ET "Bratia Minkovi"

Implementation period: 2009

Scope: Gas supply of tasting house "Izba Karnobat"

Construction of industrial heating

Read more ...

Object: "Geometal" EOOD

Implementation period: 2009

Scope: Construction of substation, internal steel pipelines and external steam lines.

Gas duct construction

Read more ...

Object: "Vins.S.Industries" OOD

Implementation period: 2009

Scope: Construction of gas duct to tasting house.

Gas installations and gas ducts

Read more ...

Object: Compressor station "Kardam"

Implementation period: 2005-2009

Scope: Complete reconstruction and modernization of gas-turbocharger agregates of compressor station "Kardam", execution of construction works, installation of new compressors and equipment, installation of steel pipelines and fixture, execution of all elecrical installations and automatization.

Gas installations and gas ducts

Read more ...

Object: Compressor station "Lozenetz"

Implementation period: 2005-2009

Scope: Complete reconstruction and modernization of gas-turbocharger agregates of compressor station "Lozenetz", execution of construction works, installation of new compressors and equipment, installation of steel pipelines and fixture, execution all Electrical installation works and automatization.

Reconstruction of agregate АС72

Read more ...

Object: "Neochim" AD

Implementation period: 2008-2009

Scope: Installation of industrial pipelines and fixture from stainless steel for scaffold bridges and industrial equipment.

Installation of stainless steel pipelines

Read more ...

Object: "Duropack Trakia Papir" AD

Implementation period: 2008

Scope: Installation of stainless steel pipelines, fittings and fixture according to isometric schemes for reconstruction of КP-23.

Installation of steel pipelines

Read more ...

Object: "Geometal" EOOD

Implementation period: 2008

Scope: Construction and erection of steel steam pipelines, condensates and water pipelines.

Construction of steam lines and gas ducts

Read more ...

Object: "Vins.S.Industries" OOD

Implementation period: 2008

Scope: Construction of platform steam lines and deviation of gas duct.

Construction of air separation installation

Read more ...

Object: "Linde Gas Bulgaria" EOOD

Implementation period: 2007

Scope: Preliminary fabrication and installation of all types carbon steel and stainless steel pipelines, construction of steel pipelines around equipment, heat insulation of steel pipelines.

Installation of steel pipelines and steel structures

Read more ...

Object: "Zagorka" AD

Implementation period: 2005

Scope: Construction of carbon steel and stainless steel pipelines, installation of vessels and production equipment.

Installation of steel pipelines and steel structures

Read more ...

Object: "Domaine Menada" AD

Implementation period: 2005

Scope: Installation of stainless steel pipelines for assemble of stainless steel vessels and equipment.

Heating and gasification of production workshop

Read more ...

Object: "Yanitza hliab"

Implementation period: 2005

Scope: Construction of heating installation and gasification of bakery production workshop.

Heating and gasification

Read more ...

Object: "Emka" AD

Implementation period: 2005

Scope: Construction of heating installation and gasification of production halls, heating with infrared heaters.

Industrial heating and gasification

Read more ...

Object: "Kemp" AD

Implementation period: 2005

Scope: Heating anf gasification of production areas with infrared heaters, panel heating.

Gasification of production workshop

Read more ...

Object: "Dijemon" EOOD

Implementation period: 2005

Scope: Construction of external and internal gasification of production workshop.